South Stand Is Growing
28.2.2007 11:37
28. 2. 20007
After the East Stand also the southern part of new Slavia stadium started to grow. „Since Monday we have been setting up the columns,“ site manager Michal Přibil from Hochtief CZ confirmed. Another crane appeared also at the site. “We have reinforced the working force at the site with the second assembly unit.“ Přibil added. At the same time the construction has been continuing in the Eastern part. „The columns are on their place, we have been assembling benches, and adding supporting joints.“Our suggestion: download the video. Have a look at photogallery. Follow the site on-line through our webcamera.
Apart from the construction of pre-fabricated constructions, “fine“ ground works have been ongoing in the site. “We have been preparing the base plate for the base under the stands. We have been digging up the earth and removing it. We have been doing the final ditches,“ Michal Pribil also said.